Agenda - Thursday, October 16, 2008

AgendaThursday, October 16, 2008 6-8 p.m.
Fort Howe Hotel & Convention Centre

1. Review of Agenda
2. Minutes of July 17, August 21 and September 18, 2008 meetings
3. Action Items from the July 17 and September 18, 2008 meetings
4. Presentation
     i) Commissioning a Pipeline (Roger Burton, Manager, Engineering for Brunswick Pipeline)
     ii) City of Saint John Projects Update – Rockwood Park Entrance (Peter Hanlon), Sewer Pumping Station @ Spar Cove (Kendall Mason), Recent Garbage Collection changes.
5. Progress Report (Robin)
6. Updates - Rockwood Park and Southwest NBCL Committees, General Project (Susan)
7. Other Items
     i) Video – Pull of 1.3 km of Pipe under St. John River
     ii) Copy of Emergency Response Plan
     iii) Winter meeting schedule
8. Next Meeting
     Thursday, November 20, 2008, Fort Howe Hotel

Mark Your Calendars: Brunswick Pipeline Christmas Reception, Thursday, December 18, 7 p.m., Hall of Great Whales, New Brunswick Museum at Market Square

Construction Activities:HDD and Pipe Pull-through
Completed, testing confirms no damage. NEB Wet Crossing hearing request to be withdrawn.

Urban - Other
Urban work remaining in Saint John includes road crossings, tying in, backfilling and initial clean-up.

Rural
Grading, trenching, stringing, welding and laying in are under way in various areas between St. Stephen and Saint John.

Brunswick Pipeline Acting Co-Chair:Robin McAdam, President
Acting Co-Chair for Brunswick Pipeline
emera.com
Office:902 428-6604 or 902 428-6243 (Ethel)
Cell: 902 499-3708

Community Co-Chair:Claude MacKinnon
rogers.com
634-8797

Contact:Susan Harris
Community Relations Manager, Brunswick Pipeline
40 Wellington Row, 2nd Floor, Saint John, NB E2L 3H3
Office: 506 693-4214
Cell: 506 654-3065
emera.com

pdf Download agenda (pdf)