Wednesday, February 27, 2008 6-9 p.m. (Supper provided)
Lily Lake Pavilion
Rockwood Park
1. Review of Agenda
2. Minutes of January 17, 2008 meeting
3. Action Items of January 17, 2008 meeting
4. Presentation – Environmental Protection Plan, Wet Crossing (Chris Blair, Jacques Whitford)
5. Updates - Rockwood Park and Southwest NB CL Committees, General Project (verbal)
6. Other Items
i. Horst Sauerteig Letter re: NEB Criteria for Detailed Route Interveners – requesting the Committee consider writing a letter to the NEB (copy attached)
ii. Horst Sauerteig Letter re: Wet Crossing Contingency Plan Questions – a response has been sent to Horst (copies attached)
7. Next Meeting - Thursday, March 13, 2007, Champlain Heights Elementary School
Rockwood Park
Clearing, Stumping & Grading: Complete
Trenching and stinging: under way
HDD
Drilling at Spar Cove Site Tent Set-up at Milford, drilling under way shortly
Urban – Other
Grading from Forbes Drive to Spar Cove
Clearing: Rural
Continuing
Robin McAdam, President
Acting Co-Chair for Brunswick Pipeline
emera.com
Office: 902 428-6604 or 902 428-6243 (Ethel)
Cell: 902 499-3708
Claude MacKinnon
rogers.com
634-8797
Community Relations Manager, Brunswick Pipeline
40 Wellington Row, 2nd Floor, Saint John, NB E2L 3H3
Office: 506 693-4214
Cell: 506 654-3065
emera.com
Download Agenda (PDF, 56 Kb)