Emera New Brunswick

Agenda - Wednesday, February 6, 2007

Agenda
Wednesday, February 6, 2007
6-8 p.m.
Smith’s Hotel, Highway 1 near St. George

1. Review of Agenda
2. Minutes of the December 5, 2007 meeting
3. Acion Items from December 5, 2007 meeting
4. Presentation: Blasting, with videos of Louisbourg Pipeline and Test Blast at Rockwood Park
5. Project Update
6. Other Items
7. Next Meeting

Upcoming Activities:Rockwood Park

Clearing Complete
Stump and root removal-1/2 complete
Clearing top soil layers – under way
Grading & Blasting – under way

HDD

Drill Tent Set-up at Spar Cove Site and Installation of Drill Casing/Set-up at Milford
Start of Pilot Hole drill

Clearing:
Rural Continuing

Brunswick Pipeline Contacts:Roger Burton, Manager, Engineering
Brunswick Pipeline
Co-Chair for Brunswick Pipeline
emera.com
Office: 902 428-6668
Cell: 902 220-5480

Community Co-Chair:Peter Fenety
94 Queen Street,
St. Andrews NB E3B 1C6
nb.sympatico.ca
506 529-1084

Contact:Susan Harris
Community Relations Manager, Brunswick Pipeline
40 Wellington Row, 2nd Floor, Saint John, NB E2L 3H3
Office: 506 693-4214
Cell: 506 654-3065
emera.com

pdf Download Agenda (PDF, 48 Kb)







Brunswick Pipeline is owned by Emera Inc., an energy company based here in the Maritimes. Find out more about Emera http://www.emera.com/.