1. Review of Agenda
2. Minutes of the February 6, 2008 meeting
3. Action Items from February 6, 2008 meeting
4. Presentation:
5. Community Investment/Sponsorship Input
6. Project Update
7. Other Items
* Monthly Construction Report
* Orthophotography Maps
8. Next Meeting
Rockwood Park
Complete: Clearing, grubbing, grading
Welding and Coating under way
Laying in of welded pipe has begun
HDD
Clearing: Rural
78% of Pilot Hole drill completed
Expect completion on available lands by Saturday,
April 5
Susan Harris
Community Relations Manager, Brunswick Pipeline
40 Wellington Row, 2nd Floor, Saint John, NB
E2L 3H3
Office: 506 693-4214
Cell: 506 654-3065
emera.com