Wednesday, Feb 6, 2008
6-8 p.m.
Smith’s Hotel, Highway 1 near St. George
1.Review of Agenda
2. Minutes of the December 5, 2007 meeting
3. Action Items from December 5, 2007 meeting
4. Presentation: Blasting, with videos of Louisbourg Pipeline and Test Blast at Rockwood Park
5. Project Update
6. Other Items
7. Next Meeting
Rockwood Park - Clearing: Complete Stump and root removal-1/2 complete Clearing top soil layers – under way Grading & Blasting – under way
HDD - Drill Tent Set-up at Spar Cove Site and Installation of Drill Casing/Set-up at Milford Start of Pilot Hole drill
Clearing: Rural - Continuing
Roger Burton, Manager, Engineering
Co-Chair for Brunswick Pipeline
emera.com
Office: 902 428-6668
Cell: 902 220-5480
Peter Fenety
Community Co-Chair for Brunswick Pipeline
94 Queen St, St Andrews,NB, E3B 1C6
emera.com
Office: 506 529-1084
Susan Harris
Community Relations Manager,Brunswick Pipeline
40 Wellington Row, 2nd Floor, Saint John, NB, E2L 3H3
Office: 506 693-4214
Cell: 506 654-3065
emera.com
Download Agenda (pdf)