Wednesday, September 10, 2008
6-8 p.m.
Vito’s Restaurant,Hazen Avenue (Uptown) Saint John
1.Review of Agenda
2. Minutes of the July 30, 2008 meeting
3. Action Items from July 30, 2008 meeting
4. Project Progress Report (Roger Burton)
5. Updates - Rockwood Park and SJCLC Committees
6. TOUR: Visit the Milford site of the St. John River Pull-through of 1.3 km of pipe.
7. Next Meeting
- St. John River HDD - 42” ream completed August 30, 2008
Overall - 60% complete, of full 145 km route
Schedule adjustment - Urban - Clearing, grading has begun at Galbraith gravel pit. 70% complete in urban; key works are road boars/crossings
- Rural Grading and trenching work is slow. Trenching, welding and laying in is caught up to trenching
Roger Burton, Manager, Engineering
Co-Chair for Brunswick Pipeline
emera.com
Office: 902 428-6668
Cell: 902 220-5480
Peter Fenety
Community Co-Chair for Brunswick Pipeline
94 Queen St, St Andrews,NB, E3B 1C6
emera.com
Office: 506 529-1084
Susan Harris
Community Relations Manager,Brunswick Pipeline
40 Wellington Row, 2nd Floor, Saint John, NB, E2L 3H3
Office: 506 693-4214
Cell: 506 654-3065
emera.com
Download Agenda (pdf)