Project development and construction cost: $500 million
Construction began in November 2007 and was completed in early 2009.
First commercial gas flow began July 16, 2009
145-km natural gas pipeline
Pipe Diameter: 30-inch (76.2 centimetre) diameter
Maximum Allowable Operating Pressure (MAOP): 1,440 pounds per square inch (psi)
Design capacity: 850,000 dekatherms per day (DTH/d)
Classification: Group 2 pipeline
Customer Base: Repsol (Negotiated rate: 25-year firm service agreement)
Open access pipeline
Regulated by the National Energy Board (NEB), and other federal and provincial authorities
Taxes: $5.8 million/year estimated (including $3.8 million NB taxes)
$5.35 million endowment invested in community projects:
$2 million endowment to support long-term operation of Rockwood Park;
$2.15 million toward renewal of the Rockwood Park entrance at Lily Lake; and
$1.2 million used in the renewal of the Canada Games Stadium at UNB Saint John.