Emera New Brunswick

Milestones

Application for the Brunswick Pipeline project was filed with the National Energy Board in May 2006.  An eight-day project hearing was held in November 2006, and the project was approved on May 31, 2007.  Construction began in November 2007 and was completed at the end of January 2009, with natural gas introduced into the pipeline February 10-12, 2009.

Commissioning of the pipeline occurred concurrently with the commissioning of the CanaportTM LNG terminal, bringing the pipeline into service on July 16, 2009.

Key project milestones include:

Right-of-way clean-up was completed on October 7, 2009.







Brunswick Pipeline is owned by Emera Inc., an energy company based here in the Maritimes. Find out more about Emera http://www.emera.com/.